The S-Curve Explained
Visualizing Cumulative Cost Over Time
A single cost number tells you where you are today. An S-curve tells you where you are heading.
What Is an S-Curve?
A cost S-curve is simply cumulative cost plotted against time. The curve is shallow at the start when work is ramping up, steep in the middle when execution is at peak intensity, and flat near the end as the project winds down. This creates the characteristic S shape.
The S shape reflects how real projects behave. You cannot instantly mobilize a full team on day one, and you cannot finish 100% of remaining work overnight. The curve captures this natural rhythm of execution.
Cumulative vs. Per-Period Cost
Per-period spend fluctuates, but cumulative cost always increases. If a project spends $60k in period 1, $150k in period 2, and $90k in period 3, the cumulative cost at each point is $60k, $210k, and $300k respectively.
Planned Value (PV), Earned Value (EV), and Actual Cost (AC) each produce their own S-curve. Plotting all three on the same graph lets you see schedule and cost health instantly: if EV sits below PV, you are behind schedule; if AC sits above EV, you are over budget.
- 1. Period 1 cumulative: $60k
- 2. Period 2 cumulative: $60k + $150k = $210k
- 3. Period 3 cumulative: $210k + $90k = $300k
- 4. Total budget (final cumulative): $300k
💡 Hint
Check your understanding
- An S-curve plots cumulative cost over time, producing a characteristic S shape.
- Cumulative cost is the running sum of per-period spend.
- PV, EV, and AC each form S-curves; comparing them reveals project health.