Cost Variance (CV)

Measuring if you are over or under budget using Earned Value

Project Cost ControlEarned Value MathFree preview
⏱️ About 12 min
Cost Variance (CV) — illustration

A project has spent $520,000, but only completed $480,000 worth of work. Is it over or under budget, and by how much?

💡
The big idea: Cost Variance (CV) measures the difference between the value of work actually performed (EV) and the actual cost to perform that work (AC).
🎯 By the end, you'll be able to
  • Define Cost Variance (CV) and its formula.
  • Calculate CV percentage (CV%).
  • Interpret the meaning of positive and negative CV values.
📎 Helpful to know first

Completion of Module 2: Tracking Cost (PV, EV, AC).

Are we over budget?

Cost Variance (CV) is the primary metric for determining if a project is over or under budget. It compares the budgeted cost of work actually performed (Earned Value) against the actual cost of that work (Actual Cost).

\[ CV = EV - AC \]

Reading the formula

The Cost Variance is simply the Earned Value (EV) minus the Actual Cost (AC). A negative CV means you spent more than the work is worth (over budget). A positive CV means you spent less than the work is worth (under budget).

⚠️ CV Percentage

You can also express CV as a percentage of the Earned Value to understand the magnitude of the variance. The formula is CV% = CV / EV. For example, a CV of -$40,000 and EV of $480,000 gives a CV% of -8.3%.

🎮 Cost Variance Calculator LIVE
Predict first: Predict first: if EV is $480,000 and AC is $520,000, what is the CV?
Adjust EV and AC to see how Cost Variance reacts.
📝 Worked example: A project has an Earned Value (EV) of $480,000 and an Actual Cost (AC) of $520,000. What is the Cost Variance (CV) and CV%?
  1. 1. Calculate CV: CV = EV - AC = $480,000 - $520,000 = -$40,000.
  2. 2. Since CV is negative, the project is over budget.
  3. 3. Calculate CV%: CV% = CV / EV = -$40,000 / $480,000 = -0.0833.
  4. 4. Convert to percentage: -8.3%.
✓ CV = -$40,000 (Over budget); CV% = -8.3%
✏️ Practice: Given an EV of $600,000 and an AC of $550,000, what is the CV?
💡 Hint
Subtract AC from EV. A positive number means under budget.
Answer
CV = $50,000

Check your understanding

1. If a project has an EV of $480,000 and an AC of $520,000, what is the Cost Variance (CV)?
CV = EV - AC = 480,000 - 520,000 = -40,000. A negative value indicates being over budget.
2. Using the figures from the previous question (EV=$480k, AC=$520k), what is the CV%?
CV% = CV / EV = -40,000 / 480,000 = -0.0833 or -8.3%.
✅ Key takeaways
  • CV = EV - AC measures cost performance.
  • A negative CV means the project is over budget.
  • CV% = CV / EV shows the relative size of the variance.
➡️ Now that you know if you are over budget, let us find out if you are behind schedule using Schedule Variance (SV).
Ready for the next step? Back to the course outline →